Data of all the meters (Sigle Phase, Three Phase started and Solar Inverter) started reporting data to Smart Grid Control Centre
Three Phase HPL Meters has been started at different Hostel locations
MDAS / MDM, system integration and home automation application software has been innstalled on the server
Advanced Metering Infrastructure (AMI) System Integration (SI) Home Automation System (HAS) servers has been installed with Operating System and necessary configuration has been done
Three Phase HPL Meters has been delivered to IIT Kanpur
Installation of New Smart Meters has been done
New Single Phase Meters again delivered to IIT Kanpur due to Communication failure of Smart Meters to the DCUs at installed locations
Communication of Single Phase Smart Meter started
Wi-Fi based home automation devices delivered to IIT Kanpur
Installation of GSM based DCUs has been done by 2nd week of February 2017
Installation of Single Phase meters is done by January 2017