LT feeders started reporting data to Smart Grid Control Centre
Started working on software updation, SLD etc
Substations of IIT Kanpur has started reporting data to the SCADA server
Substations of IIT Kanpur has started reporting data to the SCADA server
Started installation of MFM in different substations of IIT Kanpur.
Started planning for the installation of LT panels in different substations.
Material received for installation of LT panels of substations of IIT Kanpur.
Started planning to include the LT panels of substations of IIT Kanpur
All HT panels of the substations of IIT Kanpur has started reporting data to the SCADA server
SLD of IIT Kanpur power distribution network has been started
Ethernet availability for RTU panels to communicate and report data to server is done
Cable tags for connecting RTU panel relays to the substation panels is done
Testing of operation and control of substation 4, 33 kV main substation is done
Testing of operation and control of substation part 1 and part 2 is done
Testing of operation and control of substation 3, 10 is done
Testing of operation and control of substation 7, 6 and 2 is done
Testing of operation and control of substation 8 and 5 is done
Power backup for RTU is installed for substation no. 4, 3, 33kV main substation is done
Power backup for RTU is installed for substation no. 7, 5, 8, 10, 2 and 6 is done
RTU panels mounting and cable laying for connecting HT and LT panels to the RTU panel for substation no. 3 is done
Cable laying for connecting HT and LT panels to the RTU panel is done for substation no. 6, 4
Cable laying for connecting HT and LT panels to the RTU panel is done for substation no. 10, 2
Cable laying for connecting HT and LT panels to the RTU panel is done for substation no. 5, 8
Cable laying for connecting HT and LT panels to the RTU panel is done for substation no. 7
Panel mounting and relay mounting in the panels of substation no. 3 is done
RTU panels mounting in substation no. 10, 2 and 6 is done
Relay mounting and internal wiring in the panels is done in main substation 33kV
Relay mounting and internal wiring in the panels is done in substation no. 6, 2
Relay mounting and internal wiring in the panels is done in substation no. 10, 2
Relay mounting and internal wiring in the panels is done in substation no. 5, 8
RTU panels mounting for substation no. 5, 8, 4 is done
RTU panels mounting, relay placement and internal wiring in the panels is done in substation no. 7
Placement of relays and internal wiring in the panels to monitor different signals from the substations of IIT Kanpur started
Identification of RTU placement and order for RTU base is done
Survey started for installation
100 % Material Delivery to IIT Kanpur